January 9, 2013

TRAFFIC DELAY UPDATES FOR THE UPCOMING WEEKS

Final construction activities on Bunker Road, Old Bunker Road, Mitchell Road, and Field Road will continue in the upcoming weeks.

Though traffic delays at multiple locations may occur during construction time (8:00 am to 5:00 pm on weekdays), the total delay should not exceed 15 minutes collectively.

Updated information on Phase 2 construction and projected scheduling will be regularly posted here on the project website www.projectheadlands.gov.

Follow us on Twitter @ProjectHeadland.

If you would like to be removed from or added to this distribution list, or have any questions, please respond by email to projectheadlands@dot.gov.

________________________________________________

 

December 17, 2013

HOLIDAYS CONSTRUCTION SCHEDULE

There will be no construction activities in the Headlands area between December 21, 2013 and January 5, 2014. Construction on Bunker Road, Old Bunker Road, and Mitchell Road will resume at 8:00 am on January 6, 2014 with potential delays of no more than 15 minutes collectively.

Happy Holidays!

Updated information on Phase 2 construction and projected scheduling will be regularly posted here on the project website www.projectheadlands.gov.

Follow us on Twitter @ProjectHeadland.

If you would like to be removed from or added to this distribution list, or have any questions, please respond by email to projectheadlands@dot.gov.

________________________________________________

 

December 6, 2013

TRAFFIC DELAY UPDATES

Road repairs on Conzelman Road between Alexander Avenue and the roundabout are anticipated to complete on Friday, December 6, 2013 and construction activities on Bunker Road will continue through mid January depending on the weather conditions.

Though traffic delays at multiple locations may occur during construction time (8:00 am to 5:00 pm), the total delay should not exceed 15 minutes collectively.

Updated information on Phase 2 construction and projected scheduling will be regularly posted here on the project website www.projectheadlands.gov.

Follow us on Twitter @ProjectHeadland.

If you would like to be removed from or added to this distribution list, or have any questions, please respond by email to projectheadlands@dot.gov.

________________________________________________

 

 

November 13, 2013

UPDATE

Seeding and mulching at Alexander Avenue, Bunker Road, Old Bunker Road, and Mitchell Road have been completed as planned. Hydromulch with bright green color was used for erosion control and native plant seed protection and as a tracer to verify ground coverage. The bright color will fade in near future.  

Road repairs on Conzelman Road between Alexander Avenue and the roundabout are anticipated to complete on Friday, November 15, 2013 and construction activities on Bunker Road will continue through mid December depending on the weather conditions.

Though traffic delays at multiple locations may occur, the total delay should not exceed 15 minutes collectively.

Updated information on Phase 2 construction and projected scheduling will be regularly posted here on the project website www.projectheadlands.gov.

Follow us on Twitter @ProjectHeadland.

If you would like to be removed from or added to this distribution list, or have any questions, please respond by email to projectheadlands@dot.gov.

________________________________________________

 

November 6, 2013

CONSTRUCTION UPDATE

Seeding and mulching is scheduled at Alexander Avenue on November 7 and November 8, 2013 between 8:00 am and 6:00 pm. Seeding and mulching will continue on Bunker and Mitchell Roads on Saturday, November 9, 2013 between 8:00 am and 6:00 pm.

Road repairs on Conzelman Road between Alexander Avenue and the roundabout are scheduled from November 12 through November 15, 2013 between 8:00 am and 6:00 pm and construction activities on Bunker Road will continue through the end of November.

Though traffic delays at multiple locations may occur, the total delay should not exceed 15 minutes collectively during this time.

Updated information on Phase 2 construction and projected scheduling will be regularly posted on the project website here at www.projectheadlands.gov.

Follow us on Twitter @ProjectHeadland.

If you would like to be removed from or added to this distribution list, or have any questions, please respond by email to projectheadlands@dot.gov.

________________________________________________

 

October 1, 2013

BUNKER ROAD PAVING AND WETLAND RESTORATION ACTIVITIES

Paving operations on Bunker Road between McCullough Road and Baker-Barry Tunnel  are scheduled to take place from Tuesday October 8, 2013 through Friday October 11, 2013 from 8:00 am through 6:00 pm.  Also note that traffic delays on Wednesday October 9, 2013 will begin at 7:00 am.  Though traffic delays at multiple locations may occur, the total delay should not exceed 15 minutes collectively during this time.


The transformation of the Fort Cronkhite Unpaved Overflow parking lot to a wetland filled with native vegetation has begun as of Monday, September 30, 2013.


As a result of this transformation the Fort Cronkhite Unpaved Overflow parking lot is now closed. Visitors who use this lot are encouraged to use the Fort Cronkhite parking lot, Mitchell Road on-street parking, and Fort Cronkhite Annex parking lot.


The wetland restoration activities include:

  • Restoration of eroded gullies
  • Placing permanent erosion control measures
  • Planting native vegetation

Once the wetland restoration activities are complete, the area will be monitored for five years and the vegetation will begin to grow over the next three to four years.

NOTICE: The Golden Gate National Recreation Area is closed until further notice due to partial federal government shutdown; however, the construction activities will continue during this time.

Updated information on Phase 2 construction and projected scheduling will be regularly posted on the project website here at www.projectheadlands.gov.

Follow us on Twitter @ProjectHeadland.

If you would like to be removed from or added to this distribution list, or have any questions, please respond by email to projectheadlands@dot.gov.

________________________________________________

 

 

September 13, 2013

CONSTRUCTION UPDATES ON BUNKER ROAD

Paving operations on Bunker Road between McCullough Road and Rodeo Lagoon Bridge start on Monday September 16, 2013 at 7:00 am through 6:00 pm. Paving operations will continue on Tuesday September 17 through Friday September 20 at 8:00 am through 6:00 pm. Though traffic delays at multiple locations may occur, the total delay should not exceed 15 minutes during this time.

Expect unpaved surface on Bunker Road between McCullough Road and the Baker-Barry Tunnel starting September 23, 2013 due to asphalt pulverization. Traffic delays on this section of Bunker Road also will not exceed 15 minutes collectively.

Updated information on Phase 2 construction and projected scheduling will be regularly posted on the project website here at www.projectheadlands.gov.

Follow us on Twitter @ProjectHeadland.

If you would like to be removed from or added to this distribution list, or have any questions, please respond by email to projectheadlands@dot.gov.

________________________________________________

 

 

August 28, 2013

FORT CRONKHITE PARKING LOT REOPENS AND UPDATES ON BUNKER ROAD CONSTRUCTION

The Fort Cronkhite paved parking lot will reopen for public parking on Saturday, August 31, 2013. Minor construction work will continue to take place in the immediate vicinity, but should not impact parking. All other public parking in the area continue to be available. 

Expect unpaved surface on Bunker Road between McCullough Road and Rodeo Lagoon Bridge starting September 5, 2013 due to asphalt pulverization and grading activities. Paving is scheduled to begin the week of September 16, 2013. Though traffic delays at multiple locations may occur, the total traffic delay should not exceed 15 minutes during this time.

Have a great Labor Day weekend!

Updated information on Phase 2 construction and projected scheduling will be regularly posted on the project website here at www.projectheadlands.gov.

Follow us on Twitter @ProjectHeadland.

If you would like to be removed from or added to this distribution list, or have any questions, please respond by email to projectheadlands@dot.gov.

________________________________________________

 

August 2, 2013

FORT CRONKHITE PARKING LOT CLOSURE

Fort Cronkhite Parking Lot is scheduled to be closed starting August 12 for reconstruction. Vehicles are advised to use Mitchell Road parking, the Fort Cronkhite Unpaved Overflow Parking Lot and the new Fort Cronkhite Annex Parking Lot during this time, click here to see a map.

Preliminary construction operations in the Fort Cronkhite parking lot start on August 5th; however, the lot will be operational during the preliminary activities.

Photos of the Alexander Avenue improvements are now available on our website; to see these photos, click here.

Updated information on Phase 2 construction and projected scheduling will be regularly posted on the project website here at www.projectheadlands.gov.

Follow us on Twitter @ProjectHeadland.

If you would like to be removed from or added to this distribution list, or have any questions, please respond by email to projectheadlands@dot.gov.

________________________________________________

 

July 10, 2013

TRAFFIC DELAY UPDATE

Expect no more than 15 minutes total delay for vehicles and bicycles on Bunker Road, Old Bunker Road, and Mitchell Road through the end of October 2013.

Work causing traffic delays on Alexander Avenue is complete. There will be minor work occurring off the roadway until July 18th, and slower speeds are advised for vehicles and bicycles.

Updated information on Phase 2 construction and projected scheduling will be regularly posted on the project website here at www.projectheadlands.gov.

Follow us on Twitter @ProjectHeadland.

If you would like to be removed from or added to this distribution list, or have any questions, please respond by email to projectheadlands@dot.gov.

________________________________________________

 

July 3, 2013

CONSTRUCTION UPDATES:  BAKER-BARRY TUNNEL REOPENED AND 4TH OF JULY CELEBRATION

Great News! The construction on Field Road and Alexander Avenue has been completed and both the Baker-Barry Tunnel and Bunker Road to McCullough Road are now open to vehicles.

Work on Mitchell Road parking starts on Monday July 8th between 8:00 AM and 5:00 PM and is currently scheduled through Tuesday July 16th.

4th of July at Golden Gate National Recreation Area

Golden Gate National Recreation Area expects heavy use of beaches, parking lots, trails, and historic sites this Fourth of July. For a safe and enjoyable holiday, please consider the following tips from the National Park Service.

  • Conzelman Road will be changed to one-way traffic exiting the Marin Headlands starting late in the afternoon to accommodate special event parking and maintain emergency access. The road will be closed when parking is full. Directly after the fireworks all roads will be redirected to only allow vehicles to exit the Headlands until the crowds subside. Watch for signs and rangers directing traffic. Expect heavy traffic and delays, and have patience. 
  • The parking lot at Fort Baker is expected to fill early, and area roadways are anticipated to have heavy congestions and delays after the fireworks.
  • Fireworks are discharged from two locations near Fisherman’s Wharf. The Marin Headlands does not offer optimum viewing. It is illegal to possess or light fireworks anywhere in GGNRA, including the beaches and parking lots. Do not bring them. Dogs can get very nervous during fireworks displays with the noise, bright flashes and crowds. Every year more pets are lost during holidays that feature fireworks than any other single day event. Please consider leaving your dogs at home where they will be much more comfortable.
  • On July 4, MUNI 76 will operate throughout the Marin Headlands until approximately 6:00 PM. The Muir Woods Route 66 Shuttle is also available.
  • Leave No Trace! On busy days including holidays, the amount of garbage generated can exceed the park’s ability to collect it, even with full-time crews working extra hours. Please consider the amount of packaging and unneeded items you bring when visiting the parks, and only take in what you can carry back out with you. 

Reminder: Muir Beach closes Monday, July 8 until the end of November for construction and restoration work.

Enjoy a safe and happy holiday weekend!

Updated information on Phase 2 construction and projected scheduling will be regularly posted on the project website here at www.projectheadlands.gov.

Follow us on Twitter @ProjectHeadland.

If you would like to be removed from or added to this distribution list, or have any questions, please respond by email to projectheadlands@dot.gov.

 

________________________________________________________________________

 

June 19, 2013

FIELD ROAD CONSTRUCTION OPERATIONS UPDATE!

The construction schedule on Field Road has been extended as shown below. Please expect delays of up to 15 minutes during the construction time.

  • Wednesday, June 19th: 8:00 a.m. to 5:00 p.m.
  • Thursday, June 20th: 8:00 a.m. to 6:00 p.m.
  • Friday, June 21st: 8:00 a.m. to 5:00 p.m.
  • Monday June 24th: 8:00 a.m. to 5:00 p.m.
  • Tuesday June 25th: 8:00 a.m. to 5:00 p.m.

The Baker-Barry Tunnel and Bunker Road to McCullough Road continue to be closed to vehicles due to unsafe conditions.  The NPS is working  to identify and complete the necessary repairs.

Updated information on Phase 2 construction and projected scheduling will be regularly posted here on the project website at www.projectheadlands.gov.

Follow us on Twitter by clicking here.

If you would like to be removed from or added to this distribution list, or have any questions, please respond by email toprojectheadlands@dot.gov

_________________________________________________________________

 

June 18, 2013

FIELD ROAD CONSTRUCTION OPERATIONS

Construction on Field Road is scheduled on Wednesday, June 19th and Thursday, June 20th from 8:00 a.m. to 5:00 p.m. Please expect delays of up to 15 minutes during this time.  

The Baker-Barry Tunnel and Bunker Road to McCullough Road continue to be closed to vehicles due to unsafe conditions.  The NPS is working  to identify and complete the necessary repairs.

Updated information on Phase 2 construction and projected scheduling will be regularly posted here on the project website at www.projectheadlands.gov.

Follow us on Twitter by clicking here.

If you would like to be removed from or added to this distribution list, or have any questions, please respond by email toprojectheadlands@dot.gov

_________________________________________________________________

 

June 6, 2013

ALEXANDER AVENUE PAVING OPERATIONS

Paving operations will be occurring on Alexander Avenue from 7:00 a.m. to 6:00 p.m. on Monday June 10th through Wednesday June 12th. Delays of up to 15 minutes are possible during this time.  

Please expect unpaved road conditions on Alexander Avenue through June 12th. For your safety, we strongly recommend that bicyclists and pedestrians use the advised detour to Sausalito to avoid Alexander Avenue.

To view a map of the advised detour to Sausalito please click here.

The Baker-Barry Tunnel and Bunker Road to McCullough Road continue to be closed to vehicles due to unsafe conditions.  The NPS is working quickly to both identify the causes of the unsafe conditions and start the necessary repairs.

Updated information on Phase 2 construction and projected scheduling will be regularly posted here on the project website.

Follow us on Twitter by clicking here.

If you would like to be removed from or added to this distribution list, or have any questions, please respond by email toprojectheadlands@dot.gov

____________________________________________________________________________________

 

May 23, 2013

MEMORIAL DAY HOLIDAY WEEKEND SCHEDULE AND BAKER-BARRY TUNNEL CLOSURE

CONSTRUCTION UPDATE:  There will be no construction activities or delays in the Marin Headlands, including Alexander Avenue, from noon Friday, May 24th through Monday May 27th. Construction activities, including truck traffic through the tunnel,  will resume on Tuesday May 28th at 8:00 am with up to 15 minute delays on Bunker Road, Old Bunker Road, and Mitchell Road.  

TUNNEL REMAINS CLOSED TO VEHICLES:  Due to unsafe conditions in the tunnel and on a portion of road, the Baker-Barry Tunnel and Bunker Road to McCullough Road will continue to be closed to all vehicles through Memorial Day. All motor vehicles must use Conzelman Road to enter and exit the Headlands. (See map for detour route)

TUNNEL BIKE ACCESS:  Bicyclists will be allowed to use the tunnel in both directions from noon on Friday May 24th through Monday May 27th. Starting back on Tuesday May 28th, bicyclists will be only allowed to use the tunnel before 8:00 am and after 5:00 pm on weekdays and all day during weekends. During construction hours of 8:00 am to 5:00 pm on weekdays, all bicycles must use Conzelman Road to enter and exit the Headlands. (See map for detour route)

To see a map of the delay areas and detours for vehicles click here.

To see a map of the delay areas and detours for bicycles click here.

Have a safe and fun Memorial Day weekend!

Updated information on Phase 2 construction and projected scheduling will be regularly posted on the project website at www.projectheadlands.gov.

Follow us on Twitter by clicking here.

If you would like to be removed from or added to this distribution list, or have any questions, please respond by email to projectheadlands@dot.gov.

________________________________________________________________

 

May 15, 2013

UNPAVED ROAD CONDITIONS AND ADVISED BICYCLE AND PEDESTRIAN DETOUR ON ALEXANDER AVE

Please expect unpaved road conditions on Alexander Avenue starting May 15th. For your safety, we strongly recommend that bicyclists and pedestrians use the advised detour to Sausalito to avoid Alexander Avenue.
To view a map of the advised detour to Sausalito please click here.

Paving operations will be occurring on Alexander Avenue from 7:00 a.m. to 6:00 p.m. on Wednesday May 22nd and Thursday May 23rd. Paving operations will continue on Friday May 24th between 7:00 a.m. and noon. Delays of up to 15 minutes are possible during those times.  

Old Bunker Road and Mitchell Road will also remain unpaved as the construction continues. Bicyclists are advised to use caution on the unpaved surfaces.

These changes will not result in any additional delays for the travelers on these roads and the maximum anticipated delays will remain as 15 minutes.

No-Cars.pngThe Baker-Barry Tunnel and Bunker Road to McCullough Road continue to be closed to vehicles due to unsafe conditions.  The NPS is working quickly to both identify the causes of the unsafe conditions and start the necessary repairs.

Updated information on Phase 2 construction and projected scheduling will be regularly posted on the project website here at www.projectheadlands.gov.

Twitter Follow us on Twitter by clicking here.

If you would like to be removed from or added to this distribution list, or have any questions, please respond by email to projectheadlands@dot.gov.

_________________________________________________________________

 

May 10, 2013

OLD BUNKER RD, MITCHELL RD, AND ALEXANDER AVE PAVEMENT UPDATES

As Phase 2 construction activities continue, please expect unpaved road conditions on Old Bunker Road and Mitchell Road. Alexander Avenue’s pavement will also be removed for road grading in the upcoming week. Bicyclists and vehicles should use caution when traveling on the unpaved surface.

These changes will not result in any additional delays for the travelers on these roads and the maximum anticipated delays will remain as 15 minutes.

No-Cars.png
The Baker-Barry Tunnel and Bunker Road to McCullough Road continue to be closed to vehicles due to unsafe conditions.  The NPS is working quickly to both identify the causes of the unsafe conditions and start the necessary repairs.

Check the Project Headlands photo gallery or click here to see the new construction photos!

Updated information on Phase 2 construction and projected scheduling will be regularly posted here on the project website.

 If you would like to be removed from or added to this distribution list, or have any questions, please respond by email to projectheadlands@dot.gov.

 

_________________________________________________________________

 

April 24, 2013

BAKER-BARRY TUNNEL CLOSURE AND DELAYS ON BUNKER ROAD

Due to unsafe conditions of the tunnel and a portion of road during construction, the Baker-Barry Tunnel and Bunker Road to McCullough Road will be closed to all vehicles except construction traffic for several weeks. All motor vehicles must use Conzelman Road to enter and exit the Headlands. (See map for detour route)

Bicyclists will be allowed to use the tunnel in both directions before 8:00 am and after 5:00 pm on weekdays and all day during weekends. During construction hours of 8:00 am to 5:00 pm on weekdays, all bicycles must use Conzelman Road to enter and exit the Headlands. (See map for detour route)

Expect no more than 15 minutes total delay on Bunker Road, Old Bunker Road, and Mitchell Road starting on April 26th through June 28th.

To see a map of the delay areas and detours for vehicles click here.

To see a map of the delay areas and detours for bicycles click here.

_________________________________________________________________

March 21, 2013

CONSTRUCTION DELAYS STARTING APRIL 1, 2013

Excavation using large equipment on Alexander Avenue starting on April 1st will result in delays (up to 15 minutes) and will continue through June 28th. Bicycles and pedestrians are advised to take a detour to Sausalito for their safety during the Alexander Avenue construction period.  There will also be minimal delays on Bunker Road, Old Bunker Road, and Mitchell Road due to grading operations starting April 1st.

  • Up to 15 minutes delays on Alexander Avenue from April 1st  to July 3rd from 8:00 am to 6:00 pm Monday through Friday
  • Minimal delays on Bunker Road, Old Bunker Road, and Mitchell Road starting April 1st from 8:00 am to 5:00 pm Monday through Friday

 

To see a map of the delay areas click here.

 

_________________________________________________________________

 

March 7, 2013

PHASE 2 PRELIMINARY CONSTRUCTION ACTIVITIES CONTINUE

Phase 2 preliminary construction work will continue from March 11th to March 29th. Minimal delays (maximum of 15 minutes) are anticipated for vehicles and bicyclists Monday through Friday during this time.

  • March 11th to 29th on Bunker Road and Mitchell Road from 9:00 am to 5:00 pm Monday through Friday
  • March 18th to 29th on Alexander Avenue from 8:00 am to 5:00 pm Monday through Friday

 

To see a map of the delay areas click here.

 

Construction Activities for Phase 2 include:

  • Finish replacing asphalt on Field Road
  • Reconstruction of the Alexander Avenue & W. Bunker Road (Danes Drive) intersection
  • Restoration of wetlands and removal of Fort Cronkhite Dirt Overflow Lot
  • Restoration of the Fort Cronkhite Parade Ground Quarry to its early phase quarry conditions to both enhance the natural resource and provide a visual reference to its historic use
  • Construction of the Smith Road Parking Lot and Fort Cronkhite Parking Lot
  • Resurfacing, restoration, and rehabilitation of Old Bunker Road, Mitchell Road, and Bunker Road (intersection of Old Bunker Road/ Mitchell Road to the Baker-Barry Tunnel)
  • Construction of the Fort Cronkhite Annex Parking Lot near the Marine Mammal Center
  • Guardrail replacement at East Bunker Road 

 

Updated information on Phase 2 construction and projected scheduling will be regularly posted here on the project website.

 

 

__________________________________________________________________

 

February 14, 2013

PHASE 2 CONSTRUCTION IS STARTING

After a long break since the completion of Phase 1, the final phase of Project Headlands construction will begin on Monday, February 25, 2013. The initial work includes clearing brush and a few trees along Alexander Avenue, Bunker Road, and Mitchell Road.
Vehicles and bicyclists can expect minimal delays (up to a maximum of 15 minutes) Monday through Friday, from February 25 through March 8: 

  • On Alexander Avenue from 8:00 am to 5:00 pm Monday through Friday
  • On Bunker Road and Mitchell Road from 9:00 am to 5:00 pm Monday through Friday

 

To see a map of the delay areas click here.

 

Construction Activities for Phase 2 include:

  • Finish replacing asphalt on Field Road
  • Reconstruction of the Alexander Avenue & W. Bunker Road (Danes Drive) intersection
  • Restoration of wetlands and removal of Fort Cronkhite Dirt Overflow Lot
  • Restoration of the Fort Cronkhite Parade Ground Quarry to its early phase quarry conditions to both enhance the natural resource and provide a visual reference to its historic use
  • Construction of the Smith Road Parking Lot and Fort Cronkhite Parking Lot
  • Resurfacing, restoration, and rehabilitation of Old Bunker Road, Mitchell Road, and Bunker Road (intersection of Old Bunker Road/ Mitchell Road to the Baker-Barry Tunnel)
  • Construction of the Fort Cronkhite Annex Parking Lot near the Marine Mammal Center
  • Guardrail replacement at East Bunker Road 

 

Updated information on Phase 2 construction and projected scheduling will be regularly posted on the project website.

 

Looking for old e-blasts? Visit our archives from 2011 and 2010.

Click here if you would like to be added to the mailing list to receive E-blasts and project updates.